West Reading officials have provided an updated timeline from UGI and their contractor for the completion of the Penn Avenue restoration and paving.

  • September 11th: Finishing concrete work in the 600 block
  • September 12th: Beginning to mill Penn Avenue beginning in the 200 block while doing concrete work in the 700 block
  • Week of September 15th: Paving and marking of Penn Avenue
    September 21st: West Reading Fall Fest


*Information above is based on preliminary reports and may change as the situation develops.